- Engineering, Procurement, Installation and Commissioning for Instrument Air System for Crude Tank Farm - Mesaieed - for Qatar Petroleum.
- Construction of 6th LNG Storage Tank for Rasgas Onshore Expansion Project - for Mitsubishi Heavy Industries, Japan.
- Civil Maintenance Services - Manpower and Equipment Supply - Client Oryx GTL.
- Installation of Equipments in 15 substations in Qatar - Client ABB AG.
- Engineering, Procurement, Fabrication & Installation of Offshore Plateau Maintenance Project (PMP) for Qatargas Operating Company.
- Procurement, Fabrication and Onshore Commissioning of AF New Upper Deck for Block-5 Field Development Project 2005 - For Maersk Oil Qatar.
- SLP Engineering, UK has awarded Qcon the Package-12 Accommodation Platforms BF, CF, EF & GC - scope of works comprises of building 4 jackets and 3 bridges, which includes construction engineering, procurement of bridges material and secondary steel for jackets. This fast track project will be executed by Qcon Marine Fabrication Yard at Mesaieed, Qatar.
- MAERSK awards Qcon the Test Production Skids Project - Scope of work includes Fabrication, Installation, Mechanical, Electrical and Instrumentation works, also includes testing and commissioning of 4 Nos. Test Production Skids.
- Construction of Melamine Plant (the largest Melamine Plant in the Middle East) and modify/revamp the existing Urea-1 Plant, including facilities.
- Supply of Manpower and Equipment Services for 3 to 5 years at Q-Chem.
- Civil Works for construction of New Control Building at Halul Island.
- 11 kV Township Network Upgrade & Substations - Construction of Substation
- Selected Building Finishing works for Dolphin Project.
- Erection, Testing and Commissioning of various Substations related to Qatar Power Transmission Phase 5.
- Replacement of Transformer & Bay Equipment at Abu Hamour and Al Sulaimi Substation.
- Feed, Engineering, Supply and Installation of Protection to Electrical Equipment at Qatargas Plants.
- Electrical works for Qatar Power Transmission System.
- Primary Electrical Substations for The Pearl, Qatar.
- Furnace Construction works for QAPCO EP2 Project.
- NGL-4 Piping works for QAPCO EP2 Project.
- Fabrication & Installation of 1 No. Offspec Gasoline Tank for QAPCO EP2 Project.
- EPIC of Instrument Air System for Crude Oil Tank farm at Mesaieed.
- EPIC of Seawater Pump Motors Soft Starters at PS2 & PS3 Offshore Platforms.
- Fabrication of Anchor Handling Tugs / Vessel (AHT) 101 & 102.
- Maintenance Contract for Mechanical Electrical automation & Civil jobs for 5 years.
- RLC 33/11 kV Main Substation and Common Cooling Water Substation modification works - JGC Middle East FZE.
- Carry out Piping replacement, Furmanite repairs for Ethylene Plant and General welding works for all plants during QAPCO general Shutdown.
- Marubeni Substation works.
- New Control Building works at Halul Island.
- Erection, Testing and Commissioning of various substation for Siemens.
- Onshore Fabrication of Bridge Landing structures, pipe supports for Flare Bridges for Maersk.
- Manpower and Equipment supply to Taisei Corporation for Qatar Dolphin Gas plant Project, Ras Laffan.
|
|
|
|
 |
|